Planning an anaerobic digestion plant usually starts with: feedstocks, gas yields and what the energy could be worth, followed by, the environmental permit. Unfortunately, the permit itself will end up deciding a surprising amount about how your plant operates (and what you’ll need to do if you ever want to change it), so you may want to make it a priority in your considerations.
If you’re not sure yet whether you need a permit at all, have a read of our guide to environmental permits first. Now, assuming you do need a permit:
Two routes to an environmental permit
In England you can permit an AD plant through either a standard rules permit or a bespoke one.
Standard rules permits are written by the Environment Agency for common activities. They have undertaken the risk assessments associated with the criteria for the type of plant covered by the permit. Your operation has to fit the description and meet every single rule, and if it does, you apply for the permit as it stands. For most operators it’s the quicker and cheaper option. The thing to be aware of is that the rules are fixed, so you can’t negotiate them or appeal the conditions.
There are four standard rules sets for anaerobic digestion. Two are aimed at on-farm plants and two cover AD installations and waste recovery operations more widely. Which applies to you typically comes down to what you’re digesting and how much of it.
For on-farm plants
- SR2021 No 9 is for on-farm AD plants with a treatment capacity of under 100 tonnes a day, accepting no more than 35,000 tonnes a year. The Environment Agency classes these as waste recovery operations.
- Once a farm plant goes over 100 tonnes a day, it becomes an installation and moves to SR2021 No 8. This is specific to farm wastes, so anything coming in from off the farm might need extra consideration.
For AD facilities more generally
- SR2021 No 7 is the general equivalent of No 9 and has the same limits: under 100 tonnes a day and no more than 35,000 tonnes a year.
- Above 100 tonnes a day, you’re looking at SR2021 No 6, which covers larger AD installations.
There is also a fifth set, SR2021 No 10, for digesting sewage sludge at wastewater treatment works. Unless you’re a water company, it’s unlikely to apply to you.
If you’re working from an older permit
You may come across references to SR2010 No 15 and 16 or SR2012 No 9 and 10. These have been withdrawn and replaced by the SR2021 sets, so they’re no longer available for new applications.
FYI: These rules apply in England. Natural Resources Wales runs its own permitting regime.
If your plant doesn’t fit quite right within any of the standard rules, because of what you’re taking in, how close you are to neighbours or protected sites, or the scale you’re working at, you’ll need a bespoke permit instead. This will be a longer process, so it’s worth getting advice early.
When a plant doesn’t fit the standard rules, it needs a bespoke permit written around that specific site. Upgrading biogas to biomethane with carbon capture and storage is one example – the current AD rules don’t allow it, so it has to have a bespoke permit.
Worth knowing:
The Environment Agency updated all four AD standard rules sets on 26 February 2026. If your permit was issued a few years ago, read the current version alongside how your site works today.
Before you apply
Check the location criteria before you do anything else. Every standard rules permit has them, and if your site falls outside them, the Environment Agency will send your application straight back!
The Environment Agency also runs a pre-application advice service, designed to catch problems before you submit it, a consultant like us can do this for you.
Planning permission is a separate process with a separate regulator, but the two often draw on the same evidence. Our post on environmental planning for SMEs covers that side in more detail.
When your permit stops fitting
A standard rules permit reflects your operation on the day you applied for it, and it won’t flex as your business grows. If you decide to run the plant differently and it no longer meets the rules, you’ll need to apply to move to a bespoke permit. Sorting that out before you make the change is far easier than doing it afterwards.
What happens outside your fence matters too. The Environment Agency gives two examples: a groundwater source protection zone being redrawn, or new houses going up near the site. Either of these examples could mean upgrading the operation or switching to bespoke.
Common concern:
“We’ve had our permit for years and nobody’s raised a problem.” That’s reassuring, but it doesn’t guarantee the permit is still fit. A quick review against the current rules can catch discrepancies and prevent more serious non-compliance problems.
What this looked like for one operator
The operator turns agricultural products and co-products into methane, which a gas turbine then converts into energy for the National Grid. Its AD plant sits near a small town, next to a poultry unit and surrounded by farmland.
We were brought in to support planning for the new digester and to apply for the environmental permit. Once it was built, the plant also needed a management system to run it.
The first job was showing that a full Environmental Impact Assessment wasn’t required. That took a fair bit of coordinating, with surveys covering noise and vibration, traffic, landscape and visual impact, Phase 1 habitat, and bats and reptiles. All of it fed into an Environmental Summary Report, which helped the planning consultant show every planning requirement had been met.
We then used the same evidence to secure a Standard Rules Environmental Permit. We stayed involved during the build, and there were a few bumps along the way. Being on hand meant we could help work through them, and the plant eventually started generating energy.
The story didn’t end when the gas started flowing. Once the plant was running, it was clear that not every permit requirement was being met. Kit and Kathryn both took on the Level 4 VRQ in Waste and Resource Management so the plant had the technical competence it needed until they had their own Technically Competent Manager.
The business was later sold and is still operating.
Why work with us on your AD permit
At this operation, getting the permit was only part of the job. Keeping the plant compliant once it was operating mattered just as much, and that’s where a management system earns its keep. We were involved from the first surveys right through to day-to-day running, so we know where things tend to slip.
If you’re planning a new digester, or you’ve started wondering whether your existing permit still fits, get in touch with our founder Kit from the Little Green Consulting team on 01379 783918 or at lgcl@littlegreenconsulting.com.
Hear what our clients have to say.
Frequently Asked Questions
What’s the difference between a standard rules and a bespoke permit?
A standard rules permit is a fixed set of Environment Agency rules for common activities, and you either meet them or you don’t. A bespoke permit is written around your own site and operation, which takes longer but allows for things the standard rules can’t.
Can I change the rules on my standard rules permit?
No. If your operation changes and stops fitting the rules, you’ll need to apply to move to a bespoke permit.
What happens if my site doesn’t meet the location criteria?
Your application comes back to you. Check the criteria before you put time into anything else.
Do I need planning permission as well as a permit?
Possibly. They’re handled separately, planning by your local authority and permits by the Environment Agency, and a new AD plant may need both.
Does biomethane upgrading with carbon capture need a different permit?
For now, yes. The standard AD rules don’t cover it, so it needs a bespoke permit.
Can you help once the permit has been issued?
Yes. We have supported the build of a number of AD plants and then helped them meet their permit requirements once it was up and running.